Managing Council Approvals
- Hamish Wakefield

- Mar 6
- 2 min read
When most clients think about obtaining a building consent, they often imagine a simple process: the architect prepares the drawings, submits them to council, and approval comes back a few weeks later.
For many years the process worked largely like this. In recent times, however, the consent process has evolved, and it now operates more like a collaborative conversation.
Once documentation is lodged, council carries out an initial review to confirm the proposal generally aligns with the New Zealand Building Code and any relevant planning requirements. Following that, applications are typically passed to dedicated plan reviewers or specialist contractors who undertake a more detailed technical assessment.
During that detailed review it is very common for councils to request clarification or additional information. These are called Requests for Further Information (RFIs).
In the past, an RFI was often seen as an indication that something was wrong with the design or that the documentation was incomplete. Today, RFIs more commonly serve as part of the review process itself. A reviewer may want something explained more clearly, or may ask for confirmation of a specific product, detail, or compliance pathway so that their approval decision-making process is fully documented.
Councils operate within a regulatory environment that places significant responsibility on them for the approvals they issue. As a result, reviewers often seek clear confirmation of certain aspects of a project during processing. Many councils also engage external reviewers to assist with this work, which can increase the level of scrutiny applied during the assessment stage.
This is now a normal part of the consent journey for projects of all sizes.
How We Approach RFIs
At HWA Architecture, we have evolved to treat RFIs as a natural stage of the consent process rather than a problem to be avoided or deficient documentation.
When questions arise, we respond by providing clarification, coordinating with consultants or suppliers where required, and updating drawings or information if necessary. Addressing these requests promptly helps keep the application progressing and ensures council has everything needed to issue consent.
Our goal is always the same: clear communication, efficient responses, and a smooth path through the approval process.
Why This Matters
Building projects sit at the intersection of design, regulation, and construction. Even with careful preparation, the consent process often involves some back-and-forth with the reviewing authority.
In many cases the conversation is less about how the building will be constructed and more about ensuring that the project clearly demonstrates compliance with the regulatory framework that governs it.
Managing this stage professionally is an important part of our role. It helps maintain momentum through the approval process, avoids unnecessary delays, and keeps the focus where it belongs, delivering a thoughtful, well-considered building.